Cristian Pistol, the general director of CNAIR, informed that the progress of the works on the two viaducts on the Nădășelu - Mihăești subsection of the Transylvania Highway has exceeded 35%. There are 330 workers and 145 machines mobilized on the site, and the works include structures, earthworks, retaining walls, and the relocation of utilities. So far, 100 beams have been constructed, and another 468 are set to be manufactured. The total value of the works is 995 million lei, funded through PNRR, with a completion deadline next year. Additionally, Pistol mentioned that on the Domnești - Adjud section, the progress has exceeded 90%.