According to CNIR, the works on subsection 3C2 Chiribiș-Biharia, spanning 28.5 km, are progressing rapidly, reaching 14% of the physical execution stage. The constructors Precon Transilvania-Citadina 98 are mobilizing 200 employees and 223 machines. The works include the completion of piles and foundations, formwork and reinforcement of concrete, as well as the consolidation of embankments. The execution complies with technical standards, ensuring the continuity of the works.