More than 300 people and 240 machines and pieces of equipment are currently working on Section 1D Joseni-Ditrău of the mountainous sector of the A8 Union Motorway, less than a month after work officially began. The announcement was made Wednesday by Horațiu Cosma, secretary of state at the Ministry of Transport and Infrastructure.
According to the official, the Romanian contractor’s mobilization is considered a very good start for the first motorway section built in Harghita County. Earthworks and embankments, reinforcement works, ground improvement, as well as work on overpasses and ecoducts are being carried out simultaneously at the construction site.
The Joseni-Ditrău section is 14.4 kilometers long and will include 18 bridges, overpasses and viaducts, three ecoducts, an interchange at Joseni, and a temporary connection to Section 2A Ditrău-Grințieș, allowing the sector to operate independently.
The works are monitored online through cameras installed at the work sites, with the footage published on the CNIR website. In addition, the contractor and the supervisor will alternate each week in producing drone footage along the entire construction site. At the same time, documentation is being prepared to authorize works on Section 2A.
According to the official, the Romanian contractor’s mobilization is considered a very good start for the first motorway section built in Harghita County. Earthworks and embankments, reinforcement works, ground improvement, as well as work on overpasses and ecoducts are being carried out simultaneously at the construction site.
The Joseni-Ditrău section is 14.4 kilometers long and will include 18 bridges, overpasses and viaducts, three ecoducts, an interchange at Joseni, and a temporary connection to Section 2A Ditrău-Grințieș, allowing the sector to operate independently.
The works are monitored online through cameras installed at the work sites, with the footage published on the CNIR website. In addition, the contractor and the supervisor will alternate each week in producing drone footage along the entire construction site. At the same time, documentation is being prepared to authorize works on Section 2A.
Sources
Peste 300 de oameni şi 240 de utilaje lucrează pe primul lot al Autostrăzii Unirii A8 montan
Moldova, la două autostrăzi distanţă de Europa: la câteva zile după ce s-a deschis A7 până la Bacău, apar primele imagini din munţi de pe A8 - 300 de oameni şi 240 de utilaje pe primul şantier
VIDEO&FOTO Sute de muncitori pe primul șantier pe sectorul montan al A8 și primul lot de autostradă construit vreodată în Harghita
Horaţiu Cosma, secretar de stat în Ministerul Transporturilor: Peste 300 de oameni şi 240 de utilaje lucrează pe primul lot al Autostrăzii Unirii A8 montan / Lucrări supravegheate online şi filmări cu drona, săptămânal
Latest News
14:12
A customer accuses Tesla of fraud after its Solar Roof system allegedly destroyed his home and caused $2.5 million in damages
13:59
MEP Claudiu Târziu claims that he was questioned for 40 minutes in Chișinău. The Border Police says it was a routine check
13:45
France remains in a “high-tension phase” due to the terrorist threat, according to national anti-terrorism prosecutor Olivier Christen
13:30
The toll of the capture of El Chapo Isidro, one of the FBI's most wanted fugitives: 4 Mexican soldiers and 7 suspected criminals killed
13:23
Paolo Bulgari died in Rome at the age of 89. The jeweler transformed the family business into a luxury brand recognized worldwide.
See more news