More than 300 people and 240 machines and pieces of equipment are currently working on Section 1D Joseni-Ditrău of the mountainous sector of the A8 Union Motorway, less than a month after work officially began. The announcement was made Wednesday by Horațiu Cosma, secretary of state at the Ministry of Transport and Infrastructure.
According to the official, the Romanian contractor’s mobilization is considered a very good start for the first motorway section built in Harghita County. Earthworks and embankments, reinforcement works, ground improvement, as well as work on overpasses and ecoducts are being carried out simultaneously at the construction site.
The Joseni-Ditrău section is 14.4 kilometers long and will include 18 bridges, overpasses and viaducts, three ecoducts, an interchange at Joseni, and a temporary connection to Section 2A Ditrău-Grințieș, allowing the sector to operate independently.
The works are monitored online through cameras installed at the work sites, with the footage published on the CNIR website. In addition, the contractor and the supervisor will alternate each week in producing drone footage along the entire construction site. At the same time, documentation is being prepared to authorize works on Section 2A.
According to the official, the Romanian contractor’s mobilization is considered a very good start for the first motorway section built in Harghita County. Earthworks and embankments, reinforcement works, ground improvement, as well as work on overpasses and ecoducts are being carried out simultaneously at the construction site.
The Joseni-Ditrău section is 14.4 kilometers long and will include 18 bridges, overpasses and viaducts, three ecoducts, an interchange at Joseni, and a temporary connection to Section 2A Ditrău-Grințieș, allowing the sector to operate independently.
The works are monitored online through cameras installed at the work sites, with the footage published on the CNIR website. In addition, the contractor and the supervisor will alternate each week in producing drone footage along the entire construction site. At the same time, documentation is being prepared to authorize works on Section 2A.
Sources
Peste 300 de oameni şi 240 de utilaje lucrează pe primul lot al Autostrăzii Unirii A8 montan
Moldova, la două autostrăzi distanţă de Europa: la câteva zile după ce s-a deschis A7 până la Bacău, apar primele imagini din munţi de pe A8 - 300 de oameni şi 240 de utilaje pe primul şantier
VIDEO&FOTO Sute de muncitori pe primul șantier pe sectorul montan al A8 și primul lot de autostradă construit vreodată în Harghita
Horaţiu Cosma, secretar de stat în Ministerul Transporturilor: Peste 300 de oameni şi 240 de utilaje lucrează pe primul lot al Autostrăzii Unirii A8 montan / Lucrări supravegheate online şi filmări cu drona, săptămânal
Latest News
08:39
J.D. Vance argues that Iran must reduce its uranium enrichment program to end the war
08:36
The Constitutional Court will examine on Wednesday the dispute between the Government and the High Court concerning the payment of magistrates’ outstanding salary arrears
08:31
Cristiano Ronaldo breaks his silence after leaving Portugal’s training camp / Calls for himself to be sanctioned and says he is not retiring from the national team
08:14
Goldman Sachs warns that diesel prices could remain high until 2027, amid a global refining shortage and low inventories
08:00
Messi bid farewell to Argentina with a goal and two assists / “It was a great honor to wear this jersey for over 20 years”
See more news