search icon
search icon
Flag Arrow Down
Română
Română
Magyar
Magyar
English
English
Français
Français
Deutsch
Deutsch
Italiano
Italiano
Español
Español
Русский
Русский
日本語
日本語
中国人
中国人

Change Language

arrow down
  • Română
    Română
  • Magyar
    Magyar
  • English
    English
  • Français
    Français
  • Deutsch
    Deutsch
  • Italiano
    Italiano
  • Español
    Español
  • Русский
    Русский
  • 日本語
    日本語
  • 中国人
    中国人
Sections
  • News
  • Exclusive
  • INSCOP Surveys
  • Podcast
  • EU
  • Diaspora
  • Republic of Moldova
  • Politics
  • Economy
  • Current Affairs
  • International
  • Sport
  • Health
  • Education
  • IT&C knowledge
  • Arts & Lifestyle
  • Opinions
  • Elections 2025
  • Environment
About Us
Contact
Privacy policy
Terms and conditions
Quickly scroll through news digests and see how they are covered in different publications!
  • News
  • Exclusive
    • INSCOP Surveys
    • Podcast
    • EU
    • Diaspora
    • Republic of Moldova
    • Politics
    • Economy
    • Current Affairs
    • International
    • Sport
    • Health
    • Education
    • IT&C knowledge
    • Arts & Lifestyle
    • Opinions
    • Elections 2025
    • Environment
113 new news items in the last 24 hours
  1. Home
  2. Current Affairs
10 minutes ago

CNAIR announces the progress of works on all four lots of the Sibiu-Făgăraș Motorway, with progress exceeding 56% on two of them

Riana Gegiu
whatsapp
facebook
linkedin
x
copy-link copy-link
27 November 2026, 17:43
main event image
Current Affairs
Foto: Facebook.com/ Cristian Pistol
google-preference

Always see our news on Google

Work on the Sibiu–Făgăraș Motorway (A13) is advancing on all four lots, with a total length of 68 kilometers, Cristian Pistol, director general of the National Road Infrastructure Management Company (CNAIR), announced. On two of the lots, the completion rate has exceeded 56%.

The project is being carried out by contractor Makyol, while the contracts for the four lots have a total value of 6.4 billion lei, excluding VAT. The works aim to develop a new high-speed road connection between Sibiu and Făgăraș, as part of the transport infrastructure in central Romania.

According to CNAIR, all four lots must be completed in 2028. The announced progress indicates that work is under way along the entire project route, although the pace varies from one lot to another. Exceeding the 56% threshold on two of the sections is the latest indicator of the investment’s progress. The high value of the contracts and the motorway’s total length place the project among the main road infrastructure works currently under construction.

חת,
Context: preparation of the project that would connect to the Sibiu–Făgăraș motorway

Before the announcements regarding progress on the Sibiu–Făgăraș Motorway, the Government approved the technical and economic indicators for a similar project, the Brașov–Făgăraș Motorway: approximately 50 kilometers, an estimated value of 9.35 billion lei (including VAT), and a 36-month timeline. The route was to cross the localities of Codlea, Dumbrăvița, Șercaia, Șinca, and Mândra, being divided into two sections with connections via road interchanges and temporary exits toward DN1, while the investment included 52 major structures (bridges/overpasses/viaducts and cut-and-cover tunnels), in accordance with European standards.

Separately, CNAIR announced that it was preparing the tender for the construction of this Brașov–Făgăraș project after completion of the technical documentation, with an estimated construction period of 36 months. The investment value was indicated at 7.74 billion lei (excluding VAT), and the contract was to be awarded based on the FIDIC Red Book model, with safety and fauna protection objectives provided for through cut-and-cover structures/ecoduct galleries.

Sources

sursa imagine
News.ro
Cristian Pistol, CNAIR: Lucrările pe Autostrada Sibiu - Făgăraş (A13) au ajuns la un stadiu de execuţie de peste 56% pe două dintre cele patru loturi/ Finalizarea lucrărilor, programată pentru 2028 - FOTO, VIDEO
sursa imagine
Agerpres
Pistol: Autostrada Sibiu - Făgăraș avansează pe toate cele patru loturi de 68 de kilometri

Latest News

19:31

Ilie Bolojan says PNL lawmakers will not support the PSD bill that could limit access to public information

19:14

The National Agency for Drug and Addiction Policies and Coordination warns schools to avoid meetings with former users, as personal testimonies may increase risk-taking behaviors

19:05

Mihai Viteazu mayor indicted in a case involving illegally buried waste and embezzlement

18:51

The Minister of Health announced the addition of over 800 places for graduates who passed the Residency Examination

18:36

The PNL secretary general, Dan Motreanu, attacks Sorin Grindeanu over the unpaid bills and the deficit left by the PSD government

See more news

NEWS ON THE SAME TOPICS

event image
Current Affairs
CNIR announces that work on the Chiribiș-Biharia section of the A3 has reached 87% and is progressing ahead of schedule
event image
Current Affairs
CNAIR is preparing the tender for another motorway, nearly 50 kilometers long
event image
Current Affairs
Horațiu Cosma announces progress on the works on the Transylvania Motorway / The Nădășelu–Zimbor section could open in 2026
event image
Current Affairs
CNIR: Work on the Chiribiș-Biharia section of the A3 motorway has reached 90%
event image
Current Affairs
The Transport Minister announces the opening of Lot 4 of the Sibiu–Pitești Motorway in November, after 99.22% of the work has been completed
event image
Current Affairs
CNAIR announces that Lot 3 of the A7 Bacău–Pașcani Motorway has surpassed 55% physical completion
app preview
Personalized news feed, AI-powered search, and notifications in a more interactive experience.
app preview app preview
CNAIR Sibiu-Făgăraș Highway Central Romania rapid transport road infrastructure

Editor’s Recommendations

main event image
Politics
5 hours ago

Nicușor Dan walks back his statement regarding the annulment of the presidential election: “Strictly from a legal standpoint, the decision to annul the elections in November 2024 was not based directly on Russian interference”

Sources
imagine sursa
imagine sursa
main event image
Opinions
3 hours ago

Andrei Cornea: The Young, the Old and the “Still Young”

main event image
Exclusive
8 hours ago

SPECIAL Informat.ro / Romania in the European press: Top stories from the past two weeks. Drone attacks in the Black Sea dominate the agenda, while Alice Weidel once again targets Romanians

app preview
Personalized news feed, AI-powered search, and notifications in a more interactive experience.
app preview
app store badge google play badge
  • News
  • Exclusive
  • INSCOP Surveys
  • Podcast
  • EU
  • Diaspora
  • Republic of Moldova
  • Politics
  • Economy
  • Current Affairs
  • International
  • Sport
  • Health
  • Education
  • IT&C knowledge
  • Arts & Lifestyle
  • Opinions
  • Elections 2025
  • Environment
  • About Us
  • Contact
Privacy policy
Cookies Policy
Terms and conditions
Open source licenses
All rights reserved Strategic Media Team SRL

Technology in partnership with

anpc-sal anpc-sol