search icon
search icon
Flag Arrow Down
Română
Română
Magyar
Magyar
English
English
Français
Français
Deutsch
Deutsch
Italiano
Italiano
Español
Español
Русский
Русский
日本語
日本語
中国人
中国人

Change Language

arrow down
  • Română
    Română
  • Magyar
    Magyar
  • English
    English
  • Français
    Français
  • Deutsch
    Deutsch
  • Italiano
    Italiano
  • Español
    Español
  • Русский
    Русский
  • 日本語
    日本語
  • 中国人
    中国人
Sections
  • News
  • Exclusive
  • INSCOP Surveys
  • Podcast
  • EU
  • Diaspora
  • Republic of Moldova
  • Politics
  • Economy
  • Current Affairs
  • International
  • Sport
  • Health
  • Education
  • IT&C knowledge
  • Arts & Lifestyle
  • Opinions
  • Elections 2025
  • Environment
About Us
Contact
Privacy policy
Terms and conditions
Quickly scroll through news digests and see how they are covered in different publications!
  • News
  • Exclusive
    • INSCOP Surveys
    • Podcast
    • EU
    • Diaspora
    • Republic of Moldova
    • Politics
    • Economy
    • Current Affairs
    • International
    • Sport
    • Health
    • Education
    • IT&C knowledge
    • Arts & Lifestyle
    • Opinions
    • Elections 2025
    • Environment
57 new news items in the last 24 hours
  1. Home
  2. Current Affairs

CNAIR has obtained a final decision requiring WeBuild to pay 80 million lei for delays of more than 800 days on the Brăila Bridge.

Andreea Lificiu
whatsapp
facebook
linkedin
x
copy-link copy-link
19 June 2025, 21:07
main event image
Current Affairs
https://www.shutterstock.com
google-preference

Always see our news on Google

The National Road Infrastructure Administration Company (CNAIR) has obtained a final court ruling, forcing Italian builder WeBuild to pay more than 80 million lei (about €16 million) for delays of more than 800 days in the completion of the Brăila Bridge. Although the bridge was inaugurated on July 6, 2023, structural problems have already emerged, and CNAIR has demanded remedies to protect public funds and ensure the project's completion.

Sources

sursa imagine
Stirile ProTV
Despăgubiri record pentru întârzierile Podului de la Brăila. CNAIR câștigă în instanță 16 milioane de euro
sursa imagine
Gandul
CNAIR câștigă definitiv procesul privind întârzierile la Podul de la Brăila
sursa imagine
News.ro
CNAIR a câştigat definitiv procesul privind întârzierile la Podul de la Brăila, urmând să obţină penalităţi de peste 80 de milioane de lei pentru cele peste 800 de zile de întârziere în finalizarea lucrărilor
sursa imagine
Wall-street
CNAIR, victorie în procesul de 80 de milioane de lei pentru întârzierile de la Podul de la Brăila
sursa imagine
Economica
CNAIR câștigă definitiv procesul cu WeBuild privind întârzierile la podul de la Brăila. Italienii au de plată 16 mil. euro

Latest News

23:16

General Matthew Jones warns that Russia’s aggression could trigger a miscalculation with serious consequences for NATO.

22:53

The French prosecutor's office is investigating several police officers accused of violence and sexual assault at a protest in Paris

22:30

Belgian air traffic controllers will go on strike on Monday, suspending flights at airports across the country

22:15

Donald Trump has identified Stephen Miller as a possible successor in the 2028 presidential election

22:00

Police in Dâmbovița are investigating the death of a caregiver found with signs of violence and the discovery of the elderly woman’s son, hanged.

See more news

NEWS ON THE SAME TOPICS

event image
Current Affairs
The CNIR issued the Expropriation Decision for the properties along the Focșani-Brăila Express Road route, affecting 3,297 properties and an area of 8,557,483 square meters.
event image
Current Affairs
DNA Bacău is investigating the tender for the Bacău–Piatra Neamț Expressway, a contract worth more than 5 billion lei
event image
Current Affairs
The Bucharest Court of Appeal annulled the awarding of lots 1 and 2 of the Suceava–Siret Expressway and ordered CNAIR to reevaluate the bids
event image
Current Affairs
Five bids submitted to Bucharest City Hall for the reconstruction of Calicilor Bridge and the modernization of the Dâmbovița riverbanks between Unirii Square and Izvor Bridge
event image
Current Affairs
The Buzău Regional Directorate for Roads and Bridges has completed the modernization of the bridge on DN 2N in Jitia, following an investment of more than 17 million lei
event image
Current Affairs
CNAIR: Temporary technical incident in the TollRo platform / Drivers will not be penalized if they cannot pay TollRo during the disruptions
app preview
Personalized news feed, AI-powered search, and notifications in a more interactive experience.
app preview app preview
CNAIR Braila Bridge compensation

Editor’s Recommendations

main event image
Opinions
Yesterday 19:08

Sever Voinescu: The Misadventures of a Press Conference

app preview
Personalized news feed, AI-powered search, and notifications in a more interactive experience.
app preview
app store badge google play badge
  • News
  • Exclusive
  • INSCOP Surveys
  • Podcast
  • EU
  • Diaspora
  • Republic of Moldova
  • Politics
  • Economy
  • Current Affairs
  • International
  • Sport
  • Health
  • Education
  • IT&C knowledge
  • Arts & Lifestyle
  • Opinions
  • Elections 2025
  • Environment
  • About Us
  • Contact
Privacy policy
Cookies Policy
Terms and conditions
Open source licenses
All rights reserved Strategic Media Team SRL

Technology in partnership with

anpc-sal anpc-sol