search icon
search icon
Flag Arrow Down
Română
Română
Magyar
Magyar
English
English
Français
Français
Deutsch
Deutsch
Italiano
Italiano
Español
Español
Русский
Русский
日本語
日本語
中国人
中国人

Change Language

arrow down
  • Română
    Română
  • Magyar
    Magyar
  • English
    English
  • Français
    Français
  • Deutsch
    Deutsch
  • Italiano
    Italiano
  • Español
    Español
  • Русский
    Русский
  • 日本語
    日本語
  • 中国人
    中国人
Sections
  • News
  • Exclusive
  • INSCOP Surveys
  • Podcast
  • EU
  • Diaspora
  • Republic of Moldova
  • Politics
  • Economy
  • Current Affairs
  • International
  • Sport
  • Health
  • Education
  • IT&C knowledge
  • Arts & Lifestyle
  • Opinions
  • Elections 2025
  • Environment
About Us
Contact
Privacy policy
Terms and conditions
Quickly scroll through news digests and see how they are covered in different publications!
  • News
  • Exclusive
    • INSCOP Surveys
    • Podcast
    • EU
    • Diaspora
    • Republic of Moldova
    • Politics
    • Economy
    • Current Affairs
    • International
    • Sport
    • Health
    • Education
    • IT&C knowledge
    • Arts & Lifestyle
    • Opinions
    • Elections 2025
    • Environment
118 new news items in the last 24 hours
  1. Home
  2. Current Affairs

The works on the bypass of the town of Comarnic are progressing, with an estimated completion for the summer of 2026, aiming to streamline traffic on the Prahova Valley.

Sanziana Georgescu
whatsapp
facebook
linkedin
x
copy-link copy-link
18 November 2025, 15:26
main event image
Current Affairs
sursa foto: captură youtube.com/ Infra Ro
google-preference

Always see our news on Google

The bypass of the town of Comarnic, an essential project for easing traffic on the Prahova Valley, is progressing according to plan. The viaduct over the railway and the Prahova River is in the preparation stage for pouring the concrete slab, and the retaining walls are under construction. The project, funded by the Ministry of Transport through CNAIR, has a value of approximately 300 million lei and will have a length of nearly 6 kilometers, allowing a travel speed of up to 90 km/h.

Recently, the project obtained the necessary approvals for advancing the works, including approvals for the technical execution project and the revision of the feasibility study. The bypass will include three new bridges and a passage over the Prahova River and the Ploiești-Brașov railway, facilitating the quick crossing of these obstacles. At the intersections with DN1, roundabouts will be arranged to efficiently manage traffic. The completion of the bypass is expected in the summer of 2026, contributing to reducing congestion and the time spent in traffic for locals and tourists.

Sources

sursa imagine
Profit.ro
ANUNȚ Centura Comarnic a primit ultimul aviz. Când va fi gata FOTO&VIDEO
sursa imagine
Economica
FOTO Centura Comarnic: A fost emisă ultima autorizație de construire. Când va fi gata

Latest News

17:54

Radu Miruță, negative opinion for the position of Minister of Defense

17:50

Nvidia buys back $150 billion worth of shares

17:45

Alexandru Muraru announces that the PNL could refer the matter to the CCR if the Mureșan Government is rejected and snap elections are not called

17:34

A 31-year-old German man admitted that he operated the largest darknet drug marketplace, with 600,000 customers

17:21

The European Union wants to strengthen its response to Russian hybrid attacks

See more news

NEWS ON THE SAME TOPICS

event image
Current Affairs
The deadline for completing the road works on the Comarnic Belt is set around the date of August 24.
event image
Current Affairs
CNAIR is preparing the tender for another motorway, nearly 50 kilometers long
event image
Current Affairs
The works on the bypass road of the city of Buftea have reached 34% execution stage.
event image
Current Affairs
CNAIR: Traffic on the 16 kilometers of the A7 Highway, the bypass of Bacău, is temporarily closed for connection / Traffic will be diverted through the town
event image
Current Affairs
The government approves the Brașov–Făgăraș Motorway project, spanning nearly 50 kilometers and costing 9.35 billion lei
event image
Current Affairs
CNAIR announces that the tunnels on the A1 Margina–Holdea motorway have been fully excavated, while concreting of the galleries is expected to be completed by the end of the year
app preview
Personalized news feed, AI-powered search, and notifications in a more interactive experience.
app preview app preview
comarnic belt project opinion the progress of the works

Editor’s Recommendations

main event image
Current Affairs
53 minutes ago

US ambassador, after WSJ revelations about Kimberly Guilfoyle: Washington has confidence in Romania’s democracy

Sources
imagine sursa
imagine sursa
main event image
EU
2 hours ago

Romania receives seven notices from the Commission over incomplete transposition of EU directives

main event image
Current Affairs
1 hour ago

CFR Călători, 90% discount for students: What are the conditions for the 2026-2027 academic year

Sources
imagine sursa
imagine sursa
imagine sursa
imagine sursa
imagine sursa
main event image
Exclusive
5 hours ago

SPECIAL Informat.ro / Top international political topics of the past week. The US and its allies, amid tensions and renegotiations

main event image
Exclusive
6 hours ago

EXCLUSIVE: The top sports topics from the past week / Positive reactions to Gabriela Ruse’s run in Seoul

app preview
Personalized news feed, AI-powered search, and notifications in a more interactive experience.
app preview
app store badge google play badge
  • News
  • Exclusive
  • INSCOP Surveys
  • Podcast
  • EU
  • Diaspora
  • Republic of Moldova
  • Politics
  • Economy
  • Current Affairs
  • International
  • Sport
  • Health
  • Education
  • IT&C knowledge
  • Arts & Lifestyle
  • Opinions
  • Elections 2025
  • Environment
  • About Us
  • Contact
Privacy policy
Cookies Policy
Terms and conditions
Open source licenses
All rights reserved Strategic Media Team SRL

Technology in partnership with

anpc-sal anpc-sol