search icon
search icon
Flag Arrow Down
Română
Română
Magyar
Magyar
English
English
Français
Français
Deutsch
Deutsch
Italiano
Italiano
Español
Español
Русский
Русский
日本語
日本語
中国人
中国人

Change Language

arrow down
  • Română
    Română
  • Magyar
    Magyar
  • English
    English
  • Français
    Français
  • Deutsch
    Deutsch
  • Italiano
    Italiano
  • Español
    Español
  • Русский
    Русский
  • 日本語
    日本語
  • 中国人
    中国人
Sections
  • News
  • Exclusive
  • INSCOP Surveys
  • Podcast
  • EU
  • Diaspora
  • Republic of Moldova
  • Politics
  • Economy
  • Current Affairs
  • International
  • Sport
  • Health
  • Education
  • IT&C knowledge
  • Arts & Lifestyle
  • Opinions
  • Elections 2025
  • Environment
About Us
Contact
Privacy policy
Terms and conditions
Quickly scroll through news digests and see how they are covered in different publications!
  • News
  • Exclusive
    • INSCOP Surveys
    • Podcast
    • EU
    • Diaspora
    • Republic of Moldova
    • Politics
    • Economy
    • Current Affairs
    • International
    • Sport
    • Health
    • Education
    • IT&C knowledge
    • Arts & Lifestyle
    • Opinions
    • Elections 2025
    • Environment
75 new news items in the last 24 hours
  1. Home
  2. Current Affairs

Lot 1 of the A0 North Highway, built by Pizzarotti – Retter, has 764 workers and 266 mobilized machines, with completion deadlines in 2026

Ana Maria Eftene
whatsapp
facebook
linkedin
x
copy-link copy-link
13 December 2025, 18:53
main event image
Current Affairs
Foto Facebook / Irinel Ionel Scriosteanu
google-preference

Always see our news on Google

The works will be completed in two stages: the DN1-DN1a section will be opened to traffic in the first part of next year, while the DN1a-DN7 and A1 section will be completed in the autumn of 2026. The works began in March 2023 and include the completion of hydraulic works and progress in soil stabilization, fillings, and foundations. Various structures, such as passages and bridges, are at different stages of execution, with beam installation deadlines set for December 2025. The route is 17.5 km long and runs through the territories of Ilfov and Giurgiu counties.

Sources

sursa imagine
Economedia
FOTO-VIDEO Autostrada A0 Nord. Peste 760 de muncitori și 266 de utilaje mobilizate pe șantierul Lotului 1 / Secțiunea va fi dată în circulație în două etape
sursa imagine
Adevarul
Stadiul lucrărilor pe Lotul 1 al Autostrăzii A0 Nord. Când se deschide circulației
sursa imagine
Profit.ro
Peste 760 de muncitori chemați pe Autostrada Bucureștiului VIDEO&FOTO
sursa imagine
Economica
FOTO Autostrada Bucureștiului A0: Care mai este stadiul lucrărilor la lotul 1 Nord ce ar putea fi dat în trafic anul viitor - Economica.net
sursa imagine
B365
VIDEO | Stadiul lucrărilor pe șantierul Lotului 1 al Autostrăzii Bucureștiului – A0 Nord, pe care vom circula începând cu anul viitor. Va fi dat în trafic în două etape

Latest News

12:39

Men's basketball: Kristian Kullamae, guard of the Estonian national team, joins the U-BT Cluj-Napoca team after a season at Lietkabelis.

12:34

The University of Bucharest had a record number of applications in the July 2026 session, with a competition of 6.1 applications per place for bachelor's and 3 for master's.

12:32

Oana Țoiu announces discussions at the European level for increasing security in the Black Sea, after the suspension of oil deliveries from Kazakhstan

12:28

Three people were killed and four injured, including a two-year-old child, following a shooting at the 'Bite of Seattle' festival. Authorities are searching for suspects.

12:25

The EU sanctions five Iranian judges for death sentences, floggings, and trials against dissidents

See more news

NEWS ON THE SAME TOPICS

event image
Current Affairs
Bucharest Highway A0: 760 workers mobilized across the entire site of lot 1 North
event image
Current Affairs
The works on A0 North, lot 1 (Joița-Corbeanca), have reached a physical stage of 63%
event image
Current Affairs
Approximately 5,000 workers and 1,000 machines are working on the Moldova Highway A7, on the sections Focșani – Bacău – Pașcani, to meet the deadlines of the PNRR.
event image
Current Affairs
Lot 4 Pantelimon – Glina of the A0 North highway is almost completed, but it cannot be opened to traffic.
event image
Current Affairs
Horațiu Cosma announced that the physical stage of the first lot of the Unirii A8 Highway has reached 50%
event image
Current Affairs
CNAIR announces significant progress in the construction of the Moldova Motorway (A7)
app preview
Personalized news feed, AI-powered search, and notifications in a more interactive experience.
app preview app preview
USA advance workers project

Editor’s Recommendations

main event image
Politics
2 hours ago

The vacation of the parliamentarians, interrupted by the PNRR. The Parliament enters an extraordinary session for the adoption of the necessary projects.

Sources
imagine sursa
imagine sursa
imagine sursa
imagine sursa
imagine sursa
+12
main event image
International
4 hours ago

A ship sank in the Black Sea, a week after being struck by Russian forces.

Sources
imagine sursa
imagine sursa
imagine sursa
imagine sursa
imagine sursa
main event image
Opinions
4 hours ago
Editorials and opinions

Romania must grow without consuming its future / Financial discipline is not the end of development, but the beginning of economic maturity

main event image
International
58 minutes ago

BBC gains access to Trump's financial data in the defamation case

main event image
International
4 hours ago

Vladimir Putin claims that Ukraine will lose its western territories: "Lands that once belonged to Poland, Hungary, and Romania"

Sources
imagine sursa
imagine sursa
imagine sursa
imagine sursa
main event image
Exclusive
3 hours ago
Original Content

July 27, 2026. TV: What was discussed last night on the news channels

app preview
Personalized news feed, AI-powered search, and notifications in a more interactive experience.
app preview
app store badge google play badge
  • News
  • Exclusive
  • INSCOP Surveys
  • Podcast
  • EU
  • Diaspora
  • Republic of Moldova
  • Politics
  • Economy
  • Current Affairs
  • International
  • Sport
  • Health
  • Education
  • IT&C knowledge
  • Arts & Lifestyle
  • Opinions
  • Elections 2025
  • Environment
  • About Us
  • Contact
Privacy policy
Cookies Policy
Terms and conditions
Open source licenses
All rights reserved Strategic Media Team SRL

Technology in partnership with

anpc-sal anpc-sol