search icon
search icon
Flag Arrow Down
Română
Română
Magyar
Magyar
English
English
Français
Français
Deutsch
Deutsch
Italiano
Italiano
Español
Español
Русский
Русский
日本語
日本語
中国人
中国人

Change Language

arrow down
  • Română
    Română
  • Magyar
    Magyar
  • English
    English
  • Français
    Français
  • Deutsch
    Deutsch
  • Italiano
    Italiano
  • Español
    Español
  • Русский
    Русский
  • 日本語
    日本語
  • 中国人
    中国人
Sections
  • News
  • Exclusive
  • INSCOP Surveys
  • Podcast
  • EU
  • Diaspora
  • Republic of Moldova
  • Politics
  • Economy
  • Current Affairs
  • International
  • Sport
  • Health
  • Education
  • IT&C knowledge
  • Arts & Lifestyle
  • Opinions
  • Elections 2025
  • Environment
About Us
Contact
Privacy policy
Terms and conditions
Quickly scroll through news digests and see how they are covered in different publications!
  • News
  • Exclusive
    • INSCOP Surveys
    • Podcast
    • EU
    • Diaspora
    • Republic of Moldova
    • Politics
    • Economy
    • Current Affairs
    • International
    • Sport
    • Health
    • Education
    • IT&C knowledge
    • Arts & Lifestyle
    • Opinions
    • Elections 2025
    • Environment
170 new news items in the last 24 hours
  1. Home
  2. Current Affairs

Lot 1 of the A0 North Highway, built by Pizzarotti – Retter, has 764 workers and 266 mobilized machines, with completion deadlines in 2026

Ana Maria Eftene
whatsapp
facebook
linkedin
x
copy-link copy-link
13 December 2025, 18:53
main event image
Current Affairs
Foto Facebook / Irinel Ionel Scriosteanu
google-preference

Always see our news on Google

The works will be completed in two stages: the DN1-DN1a section will be opened to traffic in the first part of next year, while the DN1a-DN7 and A1 section will be completed in the autumn of 2026. The works began in March 2023 and include the completion of hydraulic works and progress in soil stabilization, fillings, and foundations. Various structures, such as passages and bridges, are at different stages of execution, with beam installation deadlines set for December 2025. The route is 17.5 km long and runs through the territories of Ilfov and Giurgiu counties.

Sources

sursa imagine
Economedia
FOTO-VIDEO Autostrada A0 Nord. Peste 760 de muncitori și 266 de utilaje mobilizate pe șantierul Lotului 1 / Secțiunea va fi dată în circulație în două etape
sursa imagine
Adevarul
Stadiul lucrărilor pe Lotul 1 al Autostrăzii A0 Nord. Când se deschide circulației
sursa imagine
Profit.ro
Peste 760 de muncitori chemați pe Autostrada Bucureștiului VIDEO&FOTO
sursa imagine
Economica
FOTO Autostrada Bucureștiului A0: Care mai este stadiul lucrărilor la lotul 1 Nord ce ar putea fi dat în trafic anul viitor - Economica.net
sursa imagine
B365
VIDEO | Stadiul lucrărilor pe șantierul Lotului 1 al Autostrăzii Bucureștiului – A0 Nord, pe care vom circula începând cu anul viitor. Va fi dat în trafic în două etape

Latest News

23:00

Sorin Grindeanu wants the position of prime minister / PSD has not “drawn red or green lines, so that we can make a traffic light”

23:00

Transelectrica launches the pilot project to digitalize the Alba Iulia substation, an investment of 476 million lei

22:53

Bolojan, on American gas: Romania supports the Vertical Corridor, but does not need LNG imports

22:50

Ilie Bolojan, on the possibility of snap elections: “They are not a magic solution to all problems. If no solution is reached, then it is the only formula through which you can move things forward”

22:45

Cătălin Predoiu warns that snap elections could deepen political instability and calls for the reconstruction of the former governing coalition

See more news

NEWS ON THE SAME TOPICS

event image
Current Affairs
Horațiu Cosma announces record mobilization on the Joseni-Ditrău section of the A8 Motorway
event image
Current Affairs
Batch 3 Afumați - Pantelimon from A0 North, almost completed
event image
Current Affairs
CNAIR announces significant progress in the construction of the Moldova Motorway (A7)
event image
Current Affairs
The CNIR approved the Technical Project for section 1D Joseni-Ditrău of the A8 Highway, and the works will begin on August 17, 2026.
event image
Current Affairs
The Secretary of State in the Ministry of Transport announced the issuance of the construction permit for the first lot of the mountain sector of the Unirii Highway A8
event image
Economy
CNAIR announces progress of over 60% on the A7 Bacău–Pașcani Motorway and the opening of at least 49 kilometers this year
app preview
Personalized news feed, AI-powered search, and notifications in a more interactive experience.
app preview app preview
USA advance workers project

Editor’s Recommendations

main event image
Economy
Yesterday 19:40

The Ministry of Finance maintains the 25% reduction in the excise duty on diesel, amid international pressures on fuel prices

Sources
imagine sursa
imagine sursa
imagine sursa
imagine sursa
main event image
Exclusive
Yesterday 09:46

EXCLUSIVE Monitorul Miniștrilor by NewsVibe: September 24–30, 2026 / Visibility boost for ministers during the week of hearings in Parliament

app preview
Personalized news feed, AI-powered search, and notifications in a more interactive experience.
app preview
app store badge google play badge
  • News
  • Exclusive
  • INSCOP Surveys
  • Podcast
  • EU
  • Diaspora
  • Republic of Moldova
  • Politics
  • Economy
  • Current Affairs
  • International
  • Sport
  • Health
  • Education
  • IT&C knowledge
  • Arts & Lifestyle
  • Opinions
  • Elections 2025
  • Environment
  • About Us
  • Contact
Privacy policy
Cookies Policy
Terms and conditions
Open source licenses
All rights reserved Strategic Media Team SRL

Technology in partnership with

anpc-sal anpc-sol