Lot 3 of the A0 North Highway, which connects Afumați to Pantelimon, has reached a physical completion rate of 91.5%, and the works are in full progress.
The section is 8.6 kilometers long and includes activities such as pouring the final asphalt layer, installing sound-absorbing panels, and safety equipment. However, the completion of the DN3 overpass above the highway remains a critical point, essential for the final acceptance of the project.
Irinel Ionel Scrioșteanu, Secretary of State in the Ministry of Transport, visited the construction site and emphasized the importance of quickly completing the works, mentioning that traffic on DN3 will be diverted to allow the construction of the ramp to Pantelimon.
The authorities are pressuring the contractor, the Chinese company China Civil Engineering Construction Corporation, to complete the section by the end of September.