Romgaz has informed that, starting from October 13, 2025, the contract with Duro Felguera for the completion of the thermal power plant in Iernut has been terminated due to non-fulfillment of contractual obligations. The project has faced delays due to the financial difficulties of the contractor, which is in insolvency. Romgaz has initiated measures to unblock the works, including direct payment to subcontractors. The plant, expected to increase energy production by 439 MW, resumed execution in August 2023, after a suspension since 2021.
Sources
Oficial! Contractul Romgaz pentru centrala de la Iernut cu Duro Felguera este reziliat
Bursă. Romgaz a reziliat contractul cu grupul spaniol Duro Felguera pentru finalizarea centralei de la Iernut din cauza întârzierilor lucrărilor
Romgaz anunță rezilierea Contractului pentru dezvoltarea centralei de la Iernut
ULTIMA ORĂ Romgaz a reziliat și contractul Iernut 2. Va finaliza singură mult-întârziata centrală de energie pe gaze de 430 MW, care trebuia să fie gata din 2020
Latest News
19:01
UDMR supports Siegfried Mureșan for prime minister / PSD votes are decisive
18:55
Mircea Abrudean salută desemnarea lui Siegfried Mureșan ca premier de către Nicușor Dan
18:44
PPC intends to acquire Flanco as it expands into the retail of electro-IT products and energy solutions
18:31
The Ukrainian Embassy is examining the closure of the Romanian-language class in Orlivka, just four days after it opened
18:21
De la autonomie strategică la independență
See more news