Prior to the court’s decision, the Galați Environmental Guard fined the companies modernizing the Danube Promenade 100,000 lei, following an unplanned inspection carried out on October 6–7. The commissioners checked how the construction site was organized, the demarcation of work areas, and the conditions established by the Environmental Agreement, ordering remedial measures so that the works could continue within the limits of the regulatory documents; the competent authority was to be notified of the non-compliances. The inspection also covered the situation of the trees, where the initial documentation provided for the removal of approximately 900 trees, while later, following the inventory and reanalysis previously ordered, solutions were found to preserve 101 trees on the site and relocate another 75 within the promenade.
Always see our news on Google
On Monday, the Bucharest Tribunal partially suspended the enforcement of several decisions by the Galați Local Council and the building permit for the modernization of the Danube Waterfront. The decision concerns the project, financed with approximately 175 million lei in European funds, and remains in effect until the court of first instance issues its ruling.
The lawsuit was filed by civic organizations Eco-Civica and Bankwatch Romania against Galați City Hall, the Galați Local Council and the Galați Environmental Protection Directorate. The court partially granted the request and suspended the enforcement of Galați Local Council Decision No. 528/28.09.2023, Decision No. 801/17.12.2024 and Building Permit No. 126/22.04.2026. The ruling is not final and may be appealed.
The project has sparked controversy because of the landscaping work and the removal of trees. Protesters claim that approximately 900 trees, including some healthy ones, are due to be cut down. The City Hall says that mainly diseased trees or those without aesthetic value will be removed and that thousands of new trees will be planted.
Work began in the summer of 2026 and is estimated to take 24 months. The project includes new walkways, cycling and running tracks, playgrounds, a skatepark, relaxation areas, viewing points, lifts and ramps for people with disabilities. A fountain, permanent food-service facilities and an area reproducing the Danube Delta in miniature are also planned. The metal sculptures along the waterfront are to be incorporated into a tourist route and architecturally lit.