The Brăila–Galați expressway, 99% complete, will no longer be inaugurated in December, as the Transport Minister recently announced. Work has been halted after cable stays and fastening elements were stolen from the bridge over the Siret River.
The first thefts were reported approximately two months ago, when several metal components went missing. Recently, thieves stole additional cable stays and fastening parts essential for supporting the bridge deck. The contractor can no longer carry out the final works, including installing and concreting the slabs on the roadway.
The CNAIR spokesperson told Adevărul that the necessary components cannot be delivered by the end of the year, meaning that work cannot continue. Under these circumstances, the inauguration is estimated for spring 2027, most likely in March or April.
The DEx6 is 10.767 kilometers long and includes three bridges, two viaducts, and an overpass. The bridge complex is 1.79 kilometers long, while the bridge over the Siret measures 307 meters. The contract, worth 449.4 million lei, was awarded to the consortium of Spedition UMB, Tehnostrade, and SA&PE Construct.
,Sources
Latest News
14:05
13:59
13:50
13:44
13:35
See more news