The Stejaru Power Plant, with a capacity of 210 MW, will be refurbished through an investment of 97.5 million euros, aiming to increase efficiency and safety in operation. The project includes the modernization of hydro aggregates and control systems, ensuring operation at updated parameters. Among the objectives are reducing downtime, monitoring operating parameters, and environmental protection. Hidroelectrica, the largest producer of green energy in Romania, will benefit from this modernization, thus contributing to the stability of the National Energy System.
Sources
Hidroelectrica a atribuit unei companii din subordinea sa contractul de retehnologizare a turbinelor mici ale Centralei Stejaru
Hidroelectrica atribuie contractul de 97,5 milioane euro pentru retehnologizarea CHE Stejaru
Hidroelectrica semnează un contract de 97,5 mil. euro pentru retehnologizarea centralei Stejaru, una dintre cele mai importante unităţi de pe râul Bistriţa
Latest News
23:05
Ilie Bolojan accuses Alexandru Rogobete of being "one of the arsonists" of the health strike.
22:40
University of Craiova, eliminated from the Champions League qualifiers after 2-2 with Levski Sofia
22:27
MIPE provided clarifications regarding the request for a service apartment from Dragoș Pîslaru
22:05
The Court of Cassation of France rejects the appeal of Paul of Romania and approves his handover to Romania
21:51
Ilie Bolojan, call to Romanians to reduce energy consumption during peak hours after the shutdown of the reactors at Cernavodă
See more news