Before hot water gradually began to return, Electrocentrale București (ELCEN) brought Bucharest West CHP Plant back into operation, safely reconnecting the plant to the National Energy System on November 15, 2026. The restart followed major damage caused by the fires in April and May 2026, and to restore operations, the 6 kV and 0.4 kV electrical installations were refurbished, a power transformer was repaired and installed, and a procurement process was launched for a backup transformer, after the final technological tests.
At the same time, supply fluctuations were being recorded across the city: Termoenergetica announced that 71% of the associations in Bucharest had hot water and heating at appropriate levels, while the remaining 29% were still not receiving services at the required level, partly because of decisions to postpone heating and production capacity constraints. In parallel, there were also works that temporarily left consumers without hot water, including in Sectors 4 and 5, as well as a breakdown on the Berceni Main Pipeline that affected Sector 4.