On 16 November, the European Commission transmitted a partially favorable preliminary assessment of Romania’s fifth payment request under the National Recovery and Resilience Plan (PNRR), worth EUR 2.67 billion. The institution considered 34 of the 37 milestones and 35 of the 38 targets satisfactorily fulfilled. The six elements assessed unfavorably concern energy, the administration of state-owned land, and support for businesses.
In brief
The Commission favorably assessed 69 of the 75 milestones and targets. Romania submitted the request on 15 August for the fifth tranche of grants and the fourth tranche of loans.
The amount requested is EUR 2.67 billion. Payment for the favorably assessed elements may follow after the opinion of the Economic and Financial Committee and a Commission decision.
The six elements assessed unfavorably concern state-owned land, renewable hydrogen, interventions on the electricity grid, the SME test, and portfolio guarantees.
Romania will have two months to submit observations from the time the reasons are communicated. Measures taken after 31 August 2026 to fulfill the milestones and targets cannot be taken into account in this procedure.
The request covers 57 milestones and targets from the grant tranche and 18 from the loan tranche. Measures assessed favorably include expanding access to high-speed internet in villages, the acquisition of cleaner vehicles by authorities, the digitalization of universities and the tax administration, and investments in renewable energy.
The Commission identified six elements for which it could not establish satisfactory fulfillment. Two concern the entry into force of acts allowing the use of state-owned land for investments in renewable energy and supporting the use of renewable hydrogen. The others concern the establishment of a single national register of state-owned land, reducing the average duration of interventions on the electricity transmission grid, applying the test concerning the impact on SMEs, and facilitating companies’ access to financing through portfolio guarantees.
The Economic and Financial Committee has four weeks to issue an opinion. The Commission may then adopt the decision authorizing payment for the favorably assessed elements. For the part relating to the six outstanding elements, the Commission is suspending the payment deadline and will communicate the reasons for the assessment. Romania will have two months from the communication to respond.
The deadline for fulfilling the milestones and targets was 31 August 2026. Romania may submit observations and evidence concerning measures completed by that date. If the unfavorable assessment is maintained, the Commission will reduce the amount corresponding to the six elements in accordance with its methodology. If they are assessed favorably following the observations, the Commission will pay the corresponding amount. Its value remains to be determined.
In parallel, the Commission is analyzing Romania’s sixth and final payment request. The two requests have separate assessments, within the timetable for closing the Recovery and Resilience Facility at the end of 2026.