Traffic on the 9.86-kilometre Section 4 Tigveni–Curtea de Argeș of the Sibiu–Pitești Motorway could open on December 3, ahead of the contractual deadline in February 2027. The opening will also mark the inauguration of Romania’s first bored motorway tunnel.
Testing of the systems at the Curtea de Argeș Tunnel, also known as the Momaia Tunnel, has been completed, and the section is technically ready, according to CNAIR Director Cristian Pistol. The tunnel is nearly 1.35 kilometres long and has more than 2,500 monitoring points.
To ensure the facility’s permanent operation, CNAIR has formed a temporary team made up of seconded employees and technicians from the Austrian contractor PORR. The institution is to hire specialised staff for the monitoring, maintenance and intervention teams.
The tunnel was built using the NATM method, which involves excavating in segments and successively reinforcing the walls with shotcrete, waterproofing and a final concrete lining. The two bores are connected by three links for emergency situations.
Once Section 4 opens, drivers will be able to travel on approximately 54 of the 122 kilometres of the Sibiu–Pitești Motorway. The contract, worth 1.678 billion lei excluding VAT, was awarded to PORR.
Sources