Before the announced overhaul outage, generating unit 5 at the Turceni Thermal Power Plant was shut down again following a boiler failure discovered at the beginning of the week in the evaporator area. Repairs were estimated to be completed by the end of the week, and the unit was subsequently reconnected to the National Energy System on October 9.
Over the past few months, Unit 5 had also experienced unplanned outages (including in August, September, and October), with the problems being associated with cracks and ruptures in the boiler, exacerbated by equipment wear and erosion caused by coal use. In August 2026, the Government approved temporarily keeping the unit available until the end of the first quarter of 2028, in the context of restructuring the energy sector.