Rail traffic will be closed between June 30 and July 29 on the Balș-Robănești route due to consolidation works on the embankment.
Sanziana Georgescu

News
sursa foto: unsplash.com
CFR SA has announced that between June 30 and July 29, rail traffic will be completely suspended between Balș and Robănești stations, for earthworks to consolidate the embankment on the CF 101 Pitești-Craiova line. The constructor will provide means of transportation for passengers. The works, estimated at 6.362 million lei, will include improvements to the railway infrastructure and protection of the embankment against rainwater. The total duration of the works is 3 months, with one month of total closure of traffic.